2013-01-18 - 5658 - Spec - Creating MRP Controllers #MRPControllers #US
SPECIFICATIONS
5658 - Creating MRP Controllers
Purpose
Creating MRP Controllers.
Admin Info
Purpose
|
Creating MRP Controllers
|
Requested By
|
Justin Davis, Saravanan Lakshmanan
|
Spec Created By
|
Adithya
|
Spec Created Date
|
01/23/2013
|
Spec QA by
|
Adithya
|
Objects
|
T024D
|
Document Status
|
Complete
|
References
Prior Tickets
Documents
Functional Requirement
The following MRP Controllers
Mass Kmart
Mass Wal-Mart
Mass Sears
Mass Target
Mass Meijer
Mass Shopko
Mass Sam's Club
West Coast Novelties
Mass 1 TBD
Mass 2 TBD
Mass 3 TBD
VS Stadiums .com
VS License
VS Chase
Customs
Mass WINGS
Mass HEB
are to be created for the plants 1410, 7410, 1416, 1420 and 8014
Note : The Requirement was changed on 01-25-2013, it was decided to delete three MRP controllers MASS 1 TBD, MASS 2 TBD, MASS 3 TBD.
Solution Summary
[Discuss this section with Requester and get approval prior to beginning work]
Configure new MRP Controllers as shown with below numbers for Plants 1410, 7410, 1416 and 8014
MRP Controller Name
|
MRP Controller
|
Mass Kmart
|
723
|
Mass Wal - Mart
|
724
|
Mass Sears
|
725
|
Mass Target
|
726
|
Mass Meijer
|
727
|
Mass Shopko
|
728
|
Mass Sam's Club
|
729
|
West Coast Novelties
|
730
|
Mass 1 TBD
|
731
|
Mass 2 TBD
|
732
|
Mass 3 TBD
|
733
|
VS Stadiums .com
|
734
|
VS License
|
735
|
VS Chase
|
736
|
Customs
|
737
|
Mass WINGS
|
738
|
Mass HEB
|
739
|
Note : As per the new requirement three MRP Controllers must be deleted,
1. 731 MASS 1 TBD
2. 732 MASS 2 TBD
3. 733 MASS 3 TBD.
and change the description for 734 from VS Stadiums .com to VS Stadiums (remove .com)
Attached file gives the List of MRP Controllers.
Copy of 5706 MRP controllers creation .xlsx
Test Plan
[List test scenarios/cases to be executed here]
|
Test Scenario
|
Expected Results
|
1
|
Verify in Table T024D
|
Newly Configured MRP Controllers must be displayed with corresponding Plants
|
Solution Details
[Provide complete technical details for configuration or programming here]
IMG --> Production --> Material Requirement Planning --> Master Data --> Define MRP Controller
Issues
Changes in the initial requirement.